Uungula Wind Farm, NSW

Uungula Wind Farm is a proposed development of up to 97 wind turbines and associated infrastructure 14 km east of Wellington, NSW, within the Central-West Orana Renewable Energy Zone.

Key Project Info

Planning and Approvals

The project received NSW Development Consent on 11 May 2021

Status

Construction is expected to commence early-mid 2022

400MW
200k+
1m+
262

Project Timeline

Step 1/13

Project identification and site selection

Identification and site selection is based on an analysis of opportunities and constraints including (but not limited to): distance to the electricity grid, wind resource and population density of the surrounding community. Our team then undertake a number of site visits and consultation with landowners in the area.

Current Stage
Projeect Feasibility2

Step 2/13

Project feasibility and technical assessments

Site-specific investigations are undertaken to assess the impacts and opportunities of the project and feedback is sought from the local community.

Current Stage
160m Mast

Step 3/13

Development Application and Environmental Impact Statement

A Development Application is made and an EIS prepared which involves a wide range of studies to consider the potential environmental and social impacts of the project.

Current Stage
Pexels pixabay 357514

Step 4/13

Public exhibition and Submissions Report

The EIS is placed on public exhibition through the NSW Department of Planning, Industry and Environment’s forum. Interested members of the public are invited to have their say during the exhibition period by way of formal submissions. A Submissions Report is then prepared by the proponent which aims to respond to the submissions received.

Current Stage
Jeremiah Wind Farm Community Open day

Step 5/13

Assessment and development consent

The project documents are assessed by the relevant government authorities. If determined, Development Consent is granted alongside a range of conditions specific to the project.

Current Stage
Pexels christina morillo 1181435

Step 6/13

Post approval, contracting and financing

A lead contractor(s) to build the project is appointed and all pre-construction approvals and consents are finalised. During this phase, the lead contractor(s) is provided with a list of local businesses that have registered their interest and capabilities through the project website.

Current Stage
Pexels pixabay 416405

Step 7/13

Procurement

During this phase our lead contractor(s) seek tenders and engage contractors and suppliers to undertake the scope of the works. Orders are then placed for major components such as the wind turbines.

Current Stage
DSCN6131

Step 8/13

Early works and design

Initial site activities commence, such as minor clearing and provision of access roads along with establishing a site construction compound. Off-site detailed design works commences in parallel.

Current Stage
4 170607 WTG wide

Step 9/13

Major civil works

During this phase of the construction the bulk of the civil works takes place. This includes the construction of new internal access roads, excavation and construction of the turbine foundations, installation of the internal electrical reticulation system, construction of the high voltage substation and main transmission line network.

Current Stage
01 Final foundation pour 2

Step 10/13

Wind turbine erection

This is where the visual aspect of the wind farm starts to emerge, with large cranes lifting the tower sections, nacelle, hub and blades into place.

Current Stage
CWP Crudine Ridge Wind Farm JOW 201125 0131

Step 11/13

Commissioning

In order to export power to the grid, each turbine is required to undergo several performance tests. It is during this stage that you will start to see turbines spinning and ultimately the whole of the wind farm complete.

Current Stage
CWP Crudine Ridge Wind Farm JOW 201125 3553

Step 12/13

Operations

The project is operating in accordance with relevant approval conditions and management plans. Compliance with conditions of approval and management plans is monitored as required throughout the life of the project.

Current Stage
CWP Sapphire Wind Farm JOW 201111 7104

Step 13/13

Decommissioning

The design life of the wind turbines will be at least 30 years. At the end of their useful life, the wind turbines and electrical equipment will be either replaced and the wind farm repowered, or the project will be decommissioned, and the site returned to its original use at the expense of the project.

Current Stage
CWP Crudine Ridge Wind Farm JOW 201125 3744
CWP Sapphire Wind Farm JOW 201111 7108

About CWP
Renewables

CWP Renewables is a renewable energy company that develops, operates and owns renewable energy assets in Australia. With proven experience and expertise across the project lifecycle, we work with local communities and our customers to lead the transition to Australia’s low-cost, low-emissions energy future.

Community Consultative Committee

The purpose of a community consultative committee (CCC) is to provide a forum for open discussion.

It is a space for us to speak with representatives from the community, the council and other stakeholders about specific matters relating to the project.

The CCC follows the NSW Department of Planning, Industry and Environment’s Community Consultative Committee Guidelines for State Significant Projects. Meeting minutes are provided below.

Uungula’s CCC was re-established in 2018. If you would like to get in touch with your local CCC member, please contact the Independent Chairperson:

Mr Garry West
garrybwest@bigpond.com


Publicly Available Documents


Local contractors and service providers are encouraged to register their interest for supplying goods and services

Contact

Project Manager

Matthew Flower
Project Manager - Uungula Wind Farm
Email: info@uungulawindfarm.com.au

Mailing Address

PO Box 1708, Newcastle, NSW 2300

Complaints and Issues Contact Point:

Tel: 02 4013 4640

Newsletter

Receive the latest Uungula Wind Farm project updates straight to your inbox